Chlorination System

Sodium Hypochlorite 3D

Sodium Hypochlorite 3D

The WA State Department of Health (DOH) directed us to install a chlorination system in August 2024. The system will have its own shed to house/mix chlorine and a metering pump to inject the disinfectant into the water supply.

In November, 2025, the PLWA Board signed a construction contract with TRICO to install the chlorination system.

The DOH is requiring us to maintain a detectable residual disinfectant concentration of at least 0.2 mg/L (0.2 parts per million) throughout the distribution system, record the chlorine level five days a week, and to report this data monthly. To support and to automate these requirements, in March, 2026 the Board approved an engineering proposal from FACET to design a chlorine data analyzer system. In April 2026, FACET performed an on-site visit to determine the location of the chlorine data analyzer system.

FACET Distribution System Chlorine Analyzer Engineering Proposal Approved 03/28/2026


FACET Review & Response to TRICO Submittal 01 12/01/2025



TRICO Submittal Transmittal 01 11/26/2025



Polnell Landing Chlorination Small Works Contract 11/21/2025 Fully Executed




In mid-Novemner 2025, the PLWA Board Approved the Construction Bid Received from TRICO Dated 11/14/2025



Updated Project Plans from FACET following Site Walk with Bidders, Received November 10, 2025




Polnell Landing Water Assn Water System, ID #54476, Island County Chlorination Design, ODW Project #25-0601,
APPROVAL



FACET Email Response to DOH and Two Included Attachments 29 Aug 2025



DOH Comment Letter and Invoice 12 Aug 2025



DOH Acknowledgement Letter 02 June 2025



FACET Chlorination Design Report 01 March 2025



 Permit Plans 01 March 2025



DOH Email Requiring Disinfectant Treatment 20 Aug 2024